auto ad

Wednesday, November 19, 2008

time and work problem

X can do a piece of work in 2 hours, while Y can do the same piece of work in 4 hours.What is the time taken if X and Y do the work together?

converting to rate (quantity of work per unit time)

X can do (1/2) of the work in one hour
Y can do (1/4)th of the work in one hour

X+Y combined can do (1/2)+(1/4)=(3/4)th of the work in one hour

therefore X and Y combined will need 1 / (3/4)
or (4/3) hours to complete the work

that is 1 hour and 20 minutes

try the following page for some formulae time and work

other word problems with some explanation


------------------------------------------------------------


disclaimer:
There is no guarantee about the data/information on this site. You use the data/information at your own risk. You use the advertisements displayed on this page at your own risk.We are not responsible for the content of external internet sites. Some of the links may not work





No comments:

Post a Comment

please leave your comments